Thanks goes out to Lars Finneseth, FCPS Project Coordinator for Construction Projects and also a Clays Mill parent.  Mr. Finneseth was able to give me an update and some explanations as to the current work being completed.

Now that the small classrooms are gone there is much work to be done to the land itself in order to begin rebuilding.  Notice that all the sidewalks and blacktop areas have been removed. 

This view is from where the Rosies were stored by the gazebo back door.  They are now being stored by what used to be Mrs. Harrington's classroom.  Notice that there is no sidewalk and the wrought iron railing is on the ground by the Rosies. 


A view of the gazebo area.  No railing or sidewalks are left and some of the trees have had to be cut back.  At this time, I am unsure of the future of the gazebo. 

This is what is left after the backhoes broke up the floor from the small classrooms. 

This view is from the bus lane sidewalk looking at where the old portables used to be.  There is no longer any foundation from the classrooms, sidewalks, swing area, or blacktop primary playground area.

Workers are now busy removing all of the top soil from the work area.  They will use fill dirt that was transported from the new Keithshire Elementary site to fill in the hole as they construct the flooring for the new classrooms. 

View from atop the fill dirt by the bus lane. 

This view is from the door of the intermediate hallway.  This is the former site of the old portables.  Workers are bringing all of the top soil to this location. 

This view is from the top of the steps to the intermediate playground.  Look at the back of the photo and you will see a makeshift 'road' that the dump truck would take to bring the dirt around and fill the middle.  According to Mr. Finneseth, the area that is being covered will ultimately be a more level area than when they began. 

Another view facing toward the front of Mary Queen's parking lot.