As work begins on the exterior walls, a trench is dug and rebar is laid for the footers. |
A layer of concrete with more rebar is laid. The plastic toppers are not permanent but rather a safety precaution while the rebar is sticking out of the concrete. |
Workers Dwayne and Hunter install the forms for the concrete that will be poured. |
Another layer of concrete is now poured. |
After the forms are removed, a singled layer of concrete block has been laid. |
Work is now beginning on the footers for the interior walls. Rebar...... |
...and then a fresh layer of cement. |
Another part of the footer but I am unsure as to why it has this shape. |