LIBRARY AND MEDIA CENTER
The library was all packed up and cleaned out by the last day of school. |
A last view of the library. |
A few items remain waiting to be moved. |
Workers begin removing the ceiling tiles in the old library. |
The new media center gets some soffett work. |
The framing for the reading center has been installed. |
Curved soffett accents over the reading center. |
The computer area is getting drywall. |
NEW OFFICE AREA
Soffetts are being drywalled in the entrance to the administrative area. |
The front doors have been installed. |
The grids for the ceiling tiles are being installed in the front vestibule. |
PRESCHOOL PLAYGROUND AND NEW PICK UP LANE
Workers laid the framing for the concrete that will go around the preschool playground. |
The concrete has been poured. |
Workers continue to work on the new pick up lane that will extend around the back of our building. |
Gravel has been laid in the new lane. |
Work has begun on demolishing the hallway as seen from the cafeteria. |
Worker, Josh Yeager, eagerly knocks down the wall by the main stairs. |
This is what remains of our old lobby. |
The ceiling in the car hallway is being renovated. |
This is the lobby area after the ceiling tiles have been removed. |
The boys' restroom by the elevator is being demolished. |
This is the main stairwell after the wall was removed. |
CAFETERIA AND GYM
Ceiling tiles were removed so that the workers could access the light panels and ductwork. |
The new doorway leading to the administrative area has been opened. |
The stage has been cleared as they prepare for demolition. |
The stage area looks very different after the ceiling tiles have been removed. |
The entry into the cafeteria |
All of the ceiling tiles and ductwork have been removed. The cafeteria was once the school gym. |
An original gym light fixture |
The workers take down the duct work. |
The next thing removed is the hardwood floor. Superintendent Darren turned the floor into piles of toothpicks. |
The area where the lunch tables sat is now rubble. |
Removing the hardwood floor |
View from the gym entry |
The stage area |
A pile of flooring waits to be removed. |
Many people didn't realize that there is a room behind the stage. It was used for storage and housed the furnace. The workers have cut a hole in the wall in order to remove the old furnace. |
The portion of the building that was between the gym and cafeteria is being torn down. (Photo by Josh Yeager) |
The area after everything was knocked down. (Photo by Josh Yeager) |
The wall has mirrors and sinks from the restrooms that were in the gym. |
The bulldozer clears away debris. |
Remains of the boys' restroom |
The view of where the gym entrance used to be. |
A backhoe removed debris in the rain. |