| These are the front windows of the lobby. The black smudge in the center is actually a bird. |
| The starburst in the ceiling of the lobby has been painted. |
| Cabinetry is being delivered to the new office area. This is where Mrs. Vogler will be. I don't know if the green wall is in its permanent location or not but the blue one is. |
Cabinets for the kindergarten rooms on the bottom level have been delivered.
| This is the doorway that leads from the new admin hallway into the old car hall. |
| The HVAC unit is being placed on the roof. |
| Much of the debris from out front has been removed. |
| This used to be the stairwell, elevator, and entrance into the teacher's workroom. |
| If you look up at the same area as above, you will see a large hole in the roof. |
| The same hole but with some dust from where they are breaking down the walls. |
| This is what remains of the stairwell. |
| This is the new classroom area that used to be Mrs. Fosson's office and the resource office. Many of us remember that room as Mrs. Roxberry's Quest room. |
| This was formerly the entrance into the cafeteria. Soon it will be our new stairwell. |
| Sorry that pictures are out of order. Josh and another worker are knocking down the brick wall that was common between the stairwell and the workroom. |
| This is the view from the former workroom entrance by the elevator. |
| Another view of the now defunct stairwell which is now the location for the new elevator. |
| This was the boys' and girls' restrooms by the elevator. Walls have been removed and a new floor has been poured. |
| Someone had fun breaking windows out of the old classrooms. |
| The doorways and windows to the library and computer lab have been bricked in. |
| The second library entrance and teachers' lounge doors have also been bricked in. |
| The embellishments in the media center have been painted. |
The embellishment above the checkout counter is a lovely shade of green.
This is looking at the far right of the new wall. The doorway leads into the new hallway formerly referred to as the "temporary hallway".
| This is the entrance to the serving line. Notice the curved embellishments. |
| This view is of the wall where the tables and windows were. Drywall for new embellishments has been added. |
| Another view of the same wall but you can now see the new doorway that leads to the lobby. |
| Another view of the same wall |
| The serving line again but you are able to see how the ceiling is changing. |
| Workers fill in the space that contained doors that led from the cafeteria to the gym. |
| The wall that was common with the gym is being prepped to house a new stage. The stage will be accessible from both the gym and cafeteria sides. |
| Workers finish off the edges of the walls that were torn down. |